TSX: DPM

Oro:

Dundee Precious Metals Announces Second Quarter 2018 Production Results

July 11, 2018

TORONTO, July 11, 2018 (GLOBE NEWSWIRE) -- Dundee Precious Metals Inc. (TSX:DPM) (“DPM” or “the Company”) announced its mine and smelter production results for the three and six months ended June 30, 2018 and confirmed the timing of the release of second quarter 2018 operating and financial results, together with the related conference call and webcast.

“We had another strong quarter at Chelopech and continue to improve performance at Tsumeb,” said Rick Howes, President and CEO. “We remain on budget with construction at our Krumovgrad gold project with production of first concentrate on track for the fourth quarter of 2018.”

Chelopech gold production is trending toward the upper end of the 2018 guidance range while copper production remains in line with 2018 guidance. Concentrate smelted at Tsumeb is also tracking in line with the Company’s 2018 guidance. 

Production Highlights

Second quarter and year-to-date 2018 mine and metals production at the Chelopech mine and complex concentrate smelted at the Tsumeb smelter are provided below.

    Chelopech   Tsumeb Year 2018 Consolidated Guidance 1
  Q2 2018 YTD 2018 Q2 2018 YTD 2018  
Ore milled(000s tonnes) 555 1,113 - - 2,100 – 2,200
Metals contained in concentrate produced    
Gold (‘000s ounces) 48 106 - - 165 – 195
Copper (million pounds) 8.5 17.8 - - 33.7 – 40.4
Payable metals in concentrate sold    
Gold (‘000s ounces) 55 90 - - 140 – 170
Copper (million pounds) 10.4 16.5 - - 31.0 – 37.0
Complex concentrate smelted(‘000s tonnes) - - 46.4 100.5  220 – 250
  1. As disclosed in Management’s Discussion and Analysis (“MD&A”) for the period ended December 31, 2017, issued on February 15, 2018 and available at www.sedar.com.

Chelopech gold production was higher than expected in the second quarter as a result of higher gold grades in the zones mined. Similarly, copper production was slightly lower than expected as a result of the same stope sequence changes that led to higher gold production. Payable metals in concentrate sold were higher than metals contained in concentrate produced due to timing of deliveries. Chelopech gold production is trending toward the upper end of the 2018 guidance range while copper production remains in line with 2018 guidance.

At Tsumeb, the 24 day annual shutdown was successfully executed as scheduled and concentrate smelted during the period was in line with expectations. The annual shutdown had been deferred from March to May due to a significantly improved refractory campaign of 15 months representing both a time and tonnage record. The smelter is now targeting an 18 month life for the current campaign which is expected to lead to further improved performance. Full year concentrate throughput is expected to be within guidance.                                                        

At Krumovgrad, construction continues, with the start of cold commissioning of the process plant area and commencement of mining operations occurring during the quarter, as planned. Mechanical and electrical installation continued at a steady rate through the quarter, and first concentrate production remains on track for late fourth quarter of 2018. The forecast capital cost remains at $164 to $168 million, compared with the original estimate of $178 million.

Second Quarter 2018 Results

The Company’s second quarter 2018 operating and financial results are expected to be released after market close on Tuesday, July 31, 2018. The press release, MD&A and consolidated financial statements will be posted on SEDAR at www.sedar.com and on the Company’s website at www.dundeeprecious.com

The Company will hold a call and webcast to discuss its second quarter results on Wednesday, August 1, 2018 at 9:00 am EDT. The call will be hosted by Rick Howes, President and Chief Executive Officer, who will be joined by Hume Kyle, Executive Vice President and Chief Financial Officer, together with other members of the executive management team. The call will be accessible via a live webcast and by telephone.

Second Quarter 2018 Call and Webcast (Listen/View only)
Date: Wednesday, August 1, 2018
Time: 9:00 am EDT
Webcast: https://edge.media-server.com/m6/p/3xxc3qbx
Canada and USA Toll Free: 1-844-264-2104
Outside Canada or USA: 1-270-823-1169
Replay: 1-855-859-2056
Replay Passcode: 6287927

About Dundee Precious Metals

Dundee Precious Metals Inc. is a Canadian based, international gold mining company engaged in the acquisition of mineral properties, exploration, development, mining and processing of precious metals. The Company's operating assets include the Chelopech operation, which produces a copper concentrate containing gold and silver and a pyrite concentrate containing gold, located east of Sofia, Bulgaria; and the Tsumeb smelter, a complex copper concentrate processing facility located in Namibia. DPM also holds interests in a number of developing gold and exploration properties located in Bulgaria, including the Krumovgrad gold project, which started construction in the fourth quarter of 2016 and is expected to commence production in the fourth quarter of 2018, Canada,Serbia and Armenia, and its 10.2% interest in Sabina Gold & Silver Corp.

Cautionary Note Regarding Forward Looking Statements

This press release contains “forward looking statements” that involve a number of risks and uncertainties. Forward looking statements include, but are not limited to, statements with respect to the estimated capital costs, operating costs and other project economics with respect to Krumovgrad; timing of development, permitting, construction, commissioning activities and commencement of production in respect of Krumovgrad; timing of further optimization work at Tsumeb and potential benefits of the rotary furnace installation; the price of gold, copper, silver and acid; toll rates; metals exposure and stockpile interest deductions; the estimation of Mineral Reserves and Mineral Resources and the realization of such mineral estimates; the timing and amount of estimated future production and output, life of mine, costs of production, cash costs and other cost measures, capital expenditures, and timing of the development of new deposits; results of economic studies; success of exploration activities; success of permitting activities; permitting time lines; currency fluctuations; requirements for additional capital; government regulation of mining and smelting operations; environmental risks; reclamation expenses; potential or anticipated outcome of title disputes or claims; and timing and possible outcome of pending litigation. Often, but not always, forward looking statements can be identified by the use of words such as “plans”, “expects”, or “does not expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “outlook”, “intends”, “anticipates”, or “does not anticipate”, or “believes”, or variations of such words and phrases or that state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward looking statements are based on the opinions and estimates of management as of the date such statements are made and they involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any other future results, performance or achievements expressed or implied by the forward looking statements. Such factors include, among others: the uncertainties with respect to the actual results of current exploration activities; actual results of current reclamation activities; conclusions of economic evaluations and economic studies; changes in project parameters as plans continue to be refined; possible variations in ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities; uncertainties inherent with conducting business in foreign jurisdictions where corruption, civil unrest, political instability and uncertainties with the rule of law may impact the Company’s activities; fluctuations in metal and acid prices, toll rates and foreign exchange rates; unanticipated title disputes; claims or litigation; limitation on insurance coverage; cyber attacks; failure to successfully integrate MineRP’s business; failure to realize projected synergies and financial results from MineRP business; risks relating to operating a technology business reliant on the ownership, protection and ongoing development of key intellectual properties; as well as those risk factors discussed or referred to in the Company’s MD&A under the heading “Risks and Uncertainties” and under the heading “Cautionary Note Regarding Forward Looking Statements” which include further details on material assumptions used to develop such forward looking statements and material risk factors that could cause actual results to differ materially from forward looking statements, and other documents (including without limitation the Company’s most recent AIF) filed from time to time with the securities regulatory authorities in all provinces and territories of Canada and available on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward looking statements, there may be other factors that cause actions, events or results not to be anticipated, estimated or intended.  There can be no assurance that forward looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Unless required by securities laws, the Company undertakes no obligation to update forward looking statements if circumstances or management’s estimates or opinions should change. Accordingly, readers are cautioned not to place undue reliance on forward looking statements.

For further information please contact:

DUNDEE PRECIOUS METALS INC.

Rick Howes
President and
Chief Executive Officer
Tel: (416) 365-2836

Janet Reid
Manager, Investor Relations
Tel: (416) 365-25479

Subscripción a actualizaciones por email
Arrow LogoREGISTRARSE